Contents - Index
Scheduling Software home


Project Time Line Window


The Project Time Line window displays all assignments of a project in a graphical time line (Gantt chart). Assignments without start dates are shown covering only the due date. You can view or edit an assignment's information by clicking the assignment.  

Each assignment can have up to three color bars. Yellow shows the start and end period originally planned (Original Start to Original End on the Assignment Information window. Red shows the most recent plan for the assignment (Start to Due/End). Blue shows the actual time used to complete the assignment (Start to Concluded). If an assignment starts before or ends after the displayed time period, < or > is shown at the ends of the time bar.



-----------
FIELDS

Project  Select the project to be displayed.  
   
Time Scale  Select the time scale to use in displaying the time line. Days, weeks, months, and quarters provide progressively less detail but a longer period.

Date  Select a date that is in the period you wish to display. The arrow buttons will move the selected date forward or back an amount determined by the time scale you selected.

------------------
ENTRY BOX

Include Secondary  Check this box to include secondary assignments in the display

---------------
BUTTONS

Insert  Create new assignment.

Blue Arrows Used to view a colored display of various versions of the plan.

      